Disabling a Budget Cap

If a budget cap has been set for a project space, any user with Admin permissions on the project space can disable the budget cap if needed. Disabling a project space's budget cap allows unlimited usage of the project space's resources.

To disable a budget cap:

  1. Access the project space's settings in one of the following ways:

    • Click the project space to open it, and then click on the project space toolbar. Or,

    • On the main Ansys Gateway powered by AWS toolbar, click to access the Administration page. Select Project spaces and then click Edit in the project space's table row.

  2. In the Project space settings dialog, select Budget in the navigation pane.

  3. Click Enable budget cap to toggle it off.

  4. Click Done to close the view.