Adding user-defined material records to an Eco Audit project
Create a custom material to use in your Eco Audit project.
Any user-defined record you create can be saved in both Selection Project (.ces) and Eco Audit Product Definition (.prd) files. All user-defined records in your project will be saved as part of the Product Definition file, not just the records included in a Product. Only user-defined records added to the MaterialUniverse table can be used in Eco Audit projects.
- A red exclamation mark may appear next to the record name in the BoM.
- Calculations which use the property may use a default value instead.
- Any options associated with the property will not appear in the BoM.
| Property | If missing: |
|---|---|
|
Generic material class |
Default value used: Other Typical % is not included in the Recycled content options. Determines which options appear under Primary process and Secondary process. |
|
Price |
Default value used: 0 |
|
Embodied energy, primary production (virgin grade) |
Default value used: 0 Cannot specify Recycled content percentage. Cannot define a custom process. |
|
Climate change (CO2-eq), primary production (virgin grade) |
Default value used: 0 Cannot specify Recycled content percentage. Cannot define a custom process. |
|
Recycle Embodied energy, recycling Climate change (CO2-eq), recycling |
Recycle is not included in the End of Life options. Typical % and user-specified percentages are not included in the Recycled content options. |
| Recycle fraction in current supply |
Typical % is not included in the Recycled content options. |
| Downcycle |
Downcycle is not included in the End of Life options. |
|
Combust for energy recovery Heat of combustion (net) Combustion CO2 |
Combustion is not included in the End of Life options. |
|
Landfill |
Landfill is not included in the End of Life options. |